PHASE 1
-
Obtain Startup Info
-
Obtain Plot Plan
-
Start Drawings
-
Order Survey
-
Truss Drawings
-
Draft Specification
-
Draft Budget
-
Submit Plan to Bank
-
Project Documents Signed
PHASE 2
-
Make Copies of Plans
-
Fill Out Permit Application
-
Energy Calculations Complete
-
Submit Permit
-
Distribute Copies of Print
-
Make Corrections for County / Redline Plans
-
Fax: Pepco Request for Temporary Power
-
Fax: Washington Gas Request for Gas Cut Off
-
Fax: Phone Request Service Removal
-
Install Temporary Power Pole
-
Washington Gas Disconnect Gas Service
-
Power Poll Inspection
-
Call: WSSC Remove Water Meter
-
Pepco Swing Power to Temporary Service Pole
-
Cap Off Water & Sewer Lines
-
Water & Sewer Cap Inspection
-
Call: Request Disconnect Letters WSSC
-
Call: Request Disconnect Letters Pepco
-
Call: Request Disconnect Letters Washington Gas
-
Order: Rodent Inspection
-
Start Working on Specs with Owner
-
Develop Floor Covering List
-
Develop Appliance List
-
Send Specs Plans to Subcontractors for Bids
-
Project Schedule
-
Request
-
Call: 2nd Chance (Home Demo)
PHASE 3
-
Demolition Permit Approval
-
Sediment Control Inspection
-
Apply: Gas Service
-
Apply: Electrical Service
-
Deliver Jiffy John
-
2nd Chance Start Work
-
Demolition of House
-
Select: Brick
-
Select: Doors, Windows, Shingles
-
Stake Out for Clearing
-
Survey & stake Lot
PHASE 4
-
List
PHASE 5
-
List
PHASE 6
-
List